India should establish a time-bound, digitally tracked defence acquisition system in which every major procurement has a defined schedule, accountable program leadership, and measurable cost and performance baselines.
Set a Timeline for Every Major Acquisition
Every major acquisition should begin with a published internal schedule covering key stages such as:
Military Requirement → Approval → Request for Proposal → Technical Evaluation → Trials → Commercial Evaluation → Contract → Delivery
Different categories of equipment will require different timelines. A fighter aircraft cannot reasonably follow the same acquisition schedule as a drone or communications system.
But every program should have a target completion date for each stage.
When a deadline is missed, the responsible authority should record the reason, revised timeline and corrective action.
Give One Program Leader Clear Accountability
Major acquisitions often involve military services, acquisition officials, finance, technical experts, testing organizations and manufacturers.
Multiple participants should not mean unclear responsibility.
Each major acquisition should have a designated Program Manager or Program Management Office responsible for coordinating the program from requirement definition through contracting and initial delivery.
That office should be accountable for maintaining the program’s schedule, cost baseline, technical requirements, risk register and decision history.
Authority should accompany accountability. Routine decisions should be delegated to the appropriate program level rather than repeatedly moving through senior committees when higher approval is not necessary.
Bring Technical Expertise in Earlier
Technical experts, operators, engineers and industry knowledge should be incorporated when requirements are being defined—not primarily after specifications have already been established.
Requirements should distinguish between:
What military capability is essential and how industry must technically deliver that capability.
Where possible, the military should specify the operational result it requires and allow competing manufacturers to propose different technological approaches.
The draft DAP 2026 already proposes involving subject experts in finalizing requirements and overseeing trials. This should become a core principle of the acquisition system.
Stop Requirements From Continually Changing
Military requirements will sometimes need to change because threats and technology change.
But unnecessary changes after procurement begins can create delays, additional costs and repeated trials.
Once an acquisition enters formal competition, significant changes to requirements should require documented justification showing:
– why the change is operationally necessary;
– its expected effect on cost;
– its expected effect on schedule; and
– why the requirement could not reasonably be incorporated in a future upgrade.
This would not prevent legitimate changes. It would make their consequences visible.
Create Different Procurement Paths for Different Technologies
India should not use one acquisition process for every type of military equipment.
Major platforms with service lives measured in decades require extensive evaluation.
Rapidly changing technologies such as drones, software, AI, communications and electronic warfare require much faster development and procurement cycles.
The draft DAP 2026 already recognizes this distinction through proposals for fast-moving, low-cost technologies, refined Fast Track Procedures and technology-readiness-based categorization.
India should institutionalize separate acquisition pathways for major strategic platforms, conventional equipment and rapidly evolving technology.
Establish Cost, Schedule and Performance Baselines
Every major defence program should establish an approved baseline covering:
Cost — Schedule — Performance
Material deviations should trigger progressively stronger review.
Minor deviations could be managed by the program office. Larger overruns should require senior review and a documented recovery plan. Programs exceeding defined cost or schedule thresholds should require explicit approval to continue in their existing form.
Programs should be capable of being redesigned, recompeted, reduced or terminated when they no longer provide sufficient military value for their cost.
Publish a Defence Procurement Performance Dashboard
Operational details and sensitive military capabilities must remain classified.
Administrative performance does not necessarily need to be.
The Ministry of Defence should publish an annual non-sensitive procurement scorecard showing measures such as:
– average time between major acquisition stages;
– percentage of programs meeting scheduled milestones;
– major program delays;
– cost growth against approved baselines;
– time from successful prototype to production order;
– time from contract signing to initial delivery; and
– major causes of procurement delay.
The objective should not be to expose military capabilities. It should be to make administrative performance measurable.